Title 38 Chapter 1a Section 306

Liens
Preconstruction and Construction Liens
Section 306
Substantial compliance.

            

38-1a-306.   Substantial compliance.

            (1) Substantial compliance with the requirements of this chapter is sufficient to claim, as applicable, a preconstruction lien or a construction lien.

            (2) Subsection (1) may not be construed to excuse compliance with or affect the requirement to file:

            (a) a notice of preconstruction service as provided in Section 38-1a-401 in order to claim a preconstruction lien; or

            (b) a preliminary notice as provided in Section 38-1a-501 in order to claim a construction lien.


Amended by Chapter 464, 2013 General Session